Flow chart for the construction of joint filling agent

2015/10/28

1. Press the prepared joint filling agent into the joint along the diagonal direction with joint filling cutter, and then remove the surplus from the tiles surface.



2. Then remove the surplus from the surface of the tile.



3. Evenly fill the agent with joint filling scraper, make it naturally dry for 1.5-2 hours, and thoroughly clean the tiles surface with wet sponge (or fabric).



4. After the joint filling agent is completely cured over 24 hours later, if there's dirt on tiles, remove it with water of tiles cleaning agent.